The U.S. Department of Energy (DOE) startup authorization allows Oklo to load nuclear fuel, conduct startup testing, and proceed toward first criticality. In just over 10 months, Oklo progressed from groundbreaking to receiving DOE startup authorization for its first reactor at the Groves site. During that period, Oklo built the reactor facility, established the operating organization, qualified personnel, implemented nuclear programs and procedures, procured fuel and major equipment from commer